1. The State Engineer may grant a temporary approval to impound.
2. An applicant may request a temporary approval to impound by submitting to the State Engineer:
(a) The reason for the necessity of a temporary approval to impound;
(b) A timetable for submitting the deficient or missing information or documents;
(c) A completed proof of completion of work cover sheet;
(d) The certification of a professional engineer that the construction is in substantial compliance with the plans and specifications as approved; and
(e) The fee for filing proof of completion of work required by NRS 533.435.
3. If the State Engineer grants a temporary approval to impound, he or she will establish a specific expiration date not to exceed 90 days after the date of the approval.
Added to NAC by St. Engineer by R124-02, eff. 5-30-2003
NRS 532.120, 533.435
Disclaimer: These regulations may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.