1. If the drilling, plugging or rehabilitation of a well described on a notice of intent is not commenced within 60 days after the Division approves the notice of intent or by the date listed on the notice of intent on which work is to commence, whichever is later, the notice of intent lapses and a new notice of intent must be submitted and approved by the Division before such activity may proceed. The new notice of intent must include the number of the lapsed notice of intent and be accompanied by the fee required pursuant to NRS 533.435.

2. After the Division receives and approves the new notice of intent, the well driller must notify the Division in writing at least 24 hours before the work will commence and then the well driller may set up the drill rig and commence drilling, plugging or rehabilitating a well.

3. The well driller shall indicate on the Well Driller's Report for the well the number of the notice of intent that the well driller last submitted for that well.

Added to NAC by St. Engineer, eff. 1-9-90; A 12-30-97; R009-06, 6-1-2006; A by R044-14, eff. 10/24/2014; A by R068-20A, eff. 12/29/2020; A by R068-20CAP, eff. 6/23/2021

NRS 534.020, 534.110

Disclaimer: These regulations may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.