Nevada Administrative Code
Chapter 519A - Reclamation of Land Subject to Mining Operations or Exploration Projects
REGULATION OF MINING OPERATIONS AND EXPLORATION PROJECTS
Reclamation of Land
Section 519A.320 - Notification by operator of completion, abandonment or suspension of work on exploration project or mining operation

Universal Citation: NV Admin Code 519A.320

Current through December 31, 2024

1. An operator shall notify the Division in writing within 90 days after an exploration project or mining operation is completed or abandoned. The notice must state the date on which the activities for reclamation included in the approved plan for reclamation will begin.

2. Except as otherwise provided in subsection 3, the operator shall notify the Division in writing within 90 days after work is suspended on an exploration project or mining operation for more than 120 days. The notice must state:

(a) The nature and reason for the suspension;

(b) The anticipated duration of the suspension; and

(c) Any event which would reasonably be expected to result in either the resumption of activities or the abandonment of the project or operation.

3. A temporary closure caused by weather conditions does not require notice pursuant to subsection 2.

Added to NAC by Environmental Comm'n, eff. 9-19-90

NRS 519A.160

Disclaimer: These regulations may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.