Nevada Administrative Code
Chapter 519A - Reclamation of Land Subject to Mining Operations or Exploration Projects
REGULATION OF MINING OPERATIONS AND EXPLORATION PROJECTS
Reclamation of Land
Section 519A.300 - Modification by Division of plan for reclamation

Universal Citation: NV Admin Code 519A.300

Current through December 31, 2024

1. The Division, on its own motion, may modify an approved plan for reclamation if:

(a) A provision of the plan is in conflict with the provisions of a specific statute;

(b) It becomes impossible or impracticable to comply with any provision of the plan; or

(c) A significant problem is discovered to exist which results or may result from compliance with any provision of the plan.

2. If the Division, on its own motion, modifies a plan it:

(a) Shall notify the operator in a manner which allows the operator sufficient time to appeal the modification; and

(b) State the time allowed for an appeal of the decision in the modified plan.

Added to NAC by Environmental Comm'n, eff. 9-19-90

NRS 519A.150, 519A.160

Disclaimer: These regulations may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.