Nevada Administrative Code
Chapter 519A - Reclamation of Land Subject to Mining Operations or Exploration Projects
REGULATION OF MINING OPERATIONS AND EXPLORATION PROJECTS
Reclamation of Land
Section 519A.295 - Procedure for operator to modify plan for reclamation

Universal Citation: NV Admin Code 519A.295

Current through December 31, 2024

1. An operator may request a modification to a plan for reclamation:

(a) By submitting to the Division a written request and those portions of the application for a permit which are applicable to the requested modification, including, without limitation, a revision to the calculated cost of executing the plan for reclamation and the amount of surety, if applicable; and

(b) For any reason, including, without limitation:
(1) A proposed change in the postmining land use;

(2) The addition of a new disturbance to the affected land; and

(3) Proposed changes to the methods and techniques which will be used for reclamation.

2. The Division shall review a request for a major modification to a plan for reclamation or a minor modification to a plan for reclamation of a mining operation and notify the applicant if additional information is required within 30 days after the receipt of the request. The notice must state the information which is required.

3. If the applicant provides additional information to complete a request, the Division shall notify the applicant if more additional information is required within 30 days after receipt of the additional information. The notice must state the additional information which is required.

4. The Division shall issue a notice of intent to allow or deny the request within 30 days after the later of:

(a) The close of the period for public comment provided in NAC 519A.190; or

(b) The receipt of the request for modification and the corresponding fees.

5. If the request for a modification is denied, the Division shall notify the applicant of:

(a) The reasons for denial; and

(b) The time allowed and procedures for appealing the decision pursuant to NAC 519A.415.

6. A request for a minor modification to a plan for reclamation of an exploration project shall be approved or denied, and the reason for denial given, within 30 days after the request for modification is submitted.

Added to NAC by Environmental Comm'n, eff. 9-19-90; A by R086-21A, eff. 2/28/2022

NRS 519A.160, 519A.230

Disclaimer: These regulations may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.