1. An operator may request a modification to a plan for reclamation:
2. The Division shall review a request for a major modification to a plan for reclamation or a minor modification to a plan for reclamation of a mining operation and notify the applicant if additional information is required within 30 days after the receipt of the request. The notice must state the information which is required.
3. If the applicant provides additional information to complete a request, the Division shall notify the applicant if more additional information is required within 30 days after receipt of the additional information. The notice must state the additional information which is required.
4. The Division shall issue a notice of intent to allow or deny the request within 30 days after the later of:
5. If the request for a modification is denied, the Division shall notify the applicant of:
6. A request for a minor modification to a plan for reclamation of an exploration project shall be approved or denied, and the reason for denial given, within 30 days after the request for modification is submitted.
Added to NAC by Environmental Comm'n, eff. 9-19-90; A by R086-21A, eff. 2/28/2022