Nevada Administrative Code
Chapter 519A - Reclamation of Land Subject to Mining Operations or Exploration Projects
REGULATION OF MINING OPERATIONS AND EXPLORATION PROJECTS
Reclamation of Land
Section 519A.285 - Time for initiation of reclamation; extension of time; completion of reclamation
Current through December 31, 2024
1. If affected land cannot practicably be reclaimed concurrently with an exploration project or mining operation, reclamation must be initiated:
2. The Division may grant one or more extensions of the time when reclamation must begin if the operator of an exploration project or mining operation demonstrates that a reasonable likelihood exists that the project or operation will resume, based on a consideration of factors including, but not limited to:
3. Once initiated, final reclamation activities must be completed as set forth in an approved plan for reclamation, unless the exploration project or mining operation is reactivated.
4. As used in this section, "process component" has the meaning ascribed to it in NAC 445A.375.
Added to NAC by Environmental Comm'n, eff. 9-19-90
NRS 519A.160