Nevada Administrative Code
Chapter 517 - Mining Claims
MAPS
Section 517.150 - Preparation of overlays

Universal Citation: NV Admin Code 517.150

Current through September 16, 2024

1. If an area of a base map becomes cluttered by a congestion of claims, an overlay of the same material and construction as the original must be prepared in the same manner and at the same scale as the base map and used for all future plotting. If that overlay becomes cluttered, additional overlays must be similarly made and used.

2. Each overlay so constructed must:

(a) Be numbered sequentially for each base map for which they are used;

(b) Include the year in which the first claim was plotted on the overlay; and

(c) Precede the base map for which it overlays.

3. No information may be included on the base map or overlay to distinguish among a lode or placer claim, mill site or tunnel right. The information may be included in the description of the claim as prescribed in NAC NRS 517.160.

Added to NAC by Dep't of Minerals, eff. 9-1-88

NRS 517.100

Disclaimer: These regulations may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.