Nevada Administrative Code
Chapter 459 - Hazardous Materials
REGULATION OF HIGHLY HAZARDOUS SUBSTANCES AND EXPLOSIVES
Permits
Section 459.953469 - Commencement of construction before issuance of permit to construct
Current through September 16, 2024
1. If the Division determines that a new process is being constructed in the interest of mitigating the effects of acutely hazardous conditions on public safety, the environment or the health of personnel, and timely implementation of the new process is critical to ensure the preservation of those objectives, the Division may allow the owner or operator to commence construction on the new process before the permit to construct is issued.
2. The owner or operator of a new process may commence construction before a permit to construct is issued if:
3. The Division may:
Added to NAC by Environmental Comm'n by R041-01, eff. 10-25-2001
NRS 459.3818, 459.3829