Nevada Administrative Code
Chapter 459 - Hazardous Materials
REGULATION OF HIGHLY HAZARDOUS SUBSTANCES AND EXPLOSIVES
Permits
Section 459.953463 - Initial review of application for permit to construct; notification of applicant concerning completeness of application
Current through September 16, 2024
1. Upon receipt of an application for a permit to construct a new process, the Division shall review the application to determine if the application includes all the information required by NAC 459.953451. Not later than 30 days after the date on which an application is received, the Division shall provide to the applicant its initial determination as to the completeness of the application.
2. If the Division determines that an application for a permit to construct does not include all the information required by NAC 459.953451, the Division shall notify the applicant of its determination and include in the notice a description or list of the deficiencies.
3. If the Division determines that an application for a permit to construct is not complete, the Division may:
Added to NAC by Environmental Comm'n by R041-01, eff. 10-25-2001
NRS 459.3818, 459.3829