1. In addition to
any other information required to be included pursuant to NAC 459.95345 to
459.953475, inclusive, an application for a permit to construct a new process
must include:
(a) A site plan, drawn to scale,
that identifies the location within the facility of the new process on a map. A
site plan must include and indicate, without limitation:
(1) The city and county roads in the area of
the facility of the new process.
(2) The area encompassing the endpoint of the
worst-case release scenarios developed pursuant to NAC 459.95366 or the area
encompassing an area extending 1 mile radially from the facility, whichever is
larger.
(3) A graphical delineation
of the endpoints of each worst-case release scenario and alternative release
scenario developed pursuant to NAC 459.95366 and 459.95368.
(4) All major roads and transportation
corridors.
(5) Routes for incoming
and outgoing raw materials and products.
(6) The location of the first responding fire
station and the hazardous materials response station. If the first responding
fire station or hazardous materials response station is located outside the
plan area, the site plan must include the address of the station and indicate
the distance and direction that the station is from the facility.
(7) The location of schools, hospitals and
other public receptors within the plan area.
(b) Plot plans of the project area, shown on
separate drawings and drawn to scale, that show:
(1) The safety systems, including, without
limitation, the locations of:
(I) Water and
tankages for other materials associated with the fire suppression
systems.
(II) The system pumps and
the routing of the distribution piping.
(III) Hydrants, monitors and other similar
fire suppression equipment.
(IV)
The detectors of toxic and combustible gases and flames.
(V) Personal protective equipment.
(VI) Major process equipment.
(2) The location of the electrical
hazardous areas. The plot plan must:
(I)
Provide the necessary elevations and include detailed drawings to distinguish
between electrically unclassified and electrically classified areas, as those
terms are defined in Article 500 of the N.F.P.A. 70, the National
Electrical Code, adopted by reference pursuant to NAC 459.95528;
and
(II) Denote the nationally
recognized code or standard upon which the drawing is based to determine the
extent of the electrically classified areas.
(c) Process flow diagrams, shown on as many
drawings as necessary, developed pursuant to NAC 459.95412. The process flow
diagrams must correspond to the material and energy balance submitted pursuant
to NAC 459.953455.
(d) Piping and
instruments diagrams, shown on as many drawings as necessary, developed
pursuant to NAC 459.95412. The piping and instrument diagrams must:
(1) Be submitted on paper that is 11 inches
by 17 inches.
(2) Be on an easily
legible scale.
(3) Cover the new
process. The Division may request that the diagrams include any associated
systems, including, without limitation, air, water, nitrogen and process drain
systems, if the Division determines that the inclusion of the additional
information is necessary to assist with the review of the process hazard
analysis.
(4) Indicate all piping,
equipment, instruments and controls.
(5) Correspond to:
(I) The process flow diagrams;
(II) The documentation concerning the control
logic and the process hazard analysis submitted pursuant to NAC 459.953455;
and
(III) The specifications
submitted pursuant to NAC 459.953459.
(e) Drawings indicating the concrete
foundations and structures related to the new process that are not subject to
the review and approval of the local building official. These drawings must
include and indicate:
(1) The preparation for
the base and subbase, including, without limitation, compaction
requirements;
(2) The requirements
relating to forms, reinforcing bars and appurtenances;
(3) The specifications relating to concrete
and grout;
(4) The requirements for
testing and inspection; and
(5) The
applicable codes, standards or industry recommended practices governing the
design and construction to be used.
(f) Drawings for the structural steel support
for the equipment and piping related to the new process that are not subject to
the review and approval of the local building official. These drawings must
include and indicate:
(1) Specifications for
the steel and bolting;
(2)
Requirements for welding, testing and inspection; and
(3) The applicable codes, standards or
industry recommended practices governing the design and construction to be
used.
2. A
drawing included pursuant to this section in an application for a permit to
construct must indicate the current revision number and date of the drawing and
be of sufficient quality so that a legible copy can be made of the drawing. If
a drawing is drawn to scale, the scale must be indicated and a bar scale must
be included.
Added to NAC by Environmental
Comm'n by R041-01, eff. 10-25-2001; A by R137-04,
2-15-2005