Section 459.95345 - Permit required for construction; preliminary meeting with Division
Universal Citation: NV Admin Code 459.95345
Current through September 16, 2024
1. Before an owner or operator of a facility may commence the construction of a new process subject to C.A.P.P., the owner or operator must obtain a permit to construct the new process from the Division pursuant to NAC 459.95345 to 459.953467, inclusive.
2. Before applying for a permit to construct a new process, the owner or operator of the process must meet with the Division to discuss:
(a) The scope of the project and
the applicable codes and standards relating to the design and construction of
the project;
(b) The requirements
for the submission of documents; and
(c) The schedule for the construction of the
project.
Added to NAC by Environmental Comm'n by R041-01, eff. 10-25-2001; A by R137-04, 2-15-2005
NRS 459.3818, 459.3829
Disclaimer: These regulations may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.