Nevada Administrative Code
Chapter 459 - Hazardous Materials
REGULATION OF HIGHLY HAZARDOUS SUBSTANCES AND EXPLOSIVES
Permits
Section 459.95345 - Permit required for construction; preliminary meeting with Division

Universal Citation: NV Admin Code 459.95345

Current through September 16, 2024

1. Before an owner or operator of a facility may commence the construction of a new process subject to C.A.P.P., the owner or operator must obtain a permit to construct the new process from the Division pursuant to NAC 459.95345 to 459.953467, inclusive.

2. Before applying for a permit to construct a new process, the owner or operator of the process must meet with the Division to discuss:

(a) The scope of the project and the applicable codes and standards relating to the design and construction of the project;

(b) The requirements for the submission of documents; and

(c) The schedule for the construction of the project.

Added to NAC by Environmental Comm'n by R041-01, eff. 10-25-2001; A by R137-04, 2-15-2005

NRS 459.3818, 459.3829

Disclaimer: These regulations may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.