Section 455.135 - Marks: Duties of excavator; re-marking; confirmation or replacement
Current through September 16, 2024
1. Until an excavation or demolition is completed, an excavator shall maintain the marks:
2. If the operator's marks are removed, obliterated, covered or otherwise become disturbed or the excavator has concerns regarding the accuracy and meaning of the operator's marks before or during an excavation or demolition, the excavator:
3. An excavator may, by submitting a notification to the association for operators, request that an operator make replacement marks in all or a portion of the affected area of the proposed excavation or demolition if the existing marks are faded but still visible and the excavator has no concerns regarding the accuracy and meaning of the operator's marks as a result of the fading.
4. An operator shall respond to a request made by an excavator pursuant to subsection 2 or 3 not later than 2 working days after receipt of the request, unless the operator and excavator agree upon a different period. An operator who complies with the provisions of this subsection is not relieved of the duty to mark his or her subsurface installations pursuant to NRS 455.133 and NAC 455.130 or any other duty imposed pursuant to this chapter.
5. An excavator who complies with the provisions of subsections 2, 3 and 4 is not relieved of the duty to maintain the marks pursuant to subsection 1 or any other duty imposed pursuant to this chapter.
Added to NAC by Pub. Utilities Comm'n by R156-03, eff. 8-25-2004; A by R153-07, 1-30-2008
NRS 455.137, 703.025, 704.260, 704.280