Nevada Administrative Code
Chapter 445A - Water Controls
UNDERGROUND INJECTION CONTROL
Permits for Underground Injection
Section 445A.8915 - General permits: Procedures to request coverage for Class V well
Current through September 16, 2024
1. A person may request coverage for a Class V well under a general permit by submitting a notice of intent to operate the well as an activity for which a general permit has been issued. A notice of intent must be submitted on a form provided by the Director and include the required fee as set forth in NAC 445A.872 and sufficient information to allow the Director to make a determination of eligibility, including:
2. If the Director approves the application, the Director shall send to the applicant a letter of authorization that acknowledges coverage of the Class V well under the general permit. A letter of authorization may include such additional requirements as the Director determines appropriate for the operation of the Class V well based on the specific characteristics of the site of the well to be covered by the general permit.
Added to NAC by Environmental Comm'n by R042-01, eff. 10-25-2001
NRS 445A.425, 445A.465, 445A.475