Nevada Administrative Code
Chapter 445A - Water Controls
UNDERGROUND INJECTION CONTROL
Construction, Operation, Monitoring and Abandonment
Section 445A.909 - Submission and contents of notice of completion; approval or denial of permission to initiate injection
Current through September 16, 2024
1. Within 30 calendar days after completion of a new injection well, the holder of a permit shall furnish the Director with a notice of completion containing the following information:
2. The deviation checks must be at sufficiently frequent intervals to ensure that vertical avenues for the movement of fluids in the form of diverging holes are not created during drilling.
3. The Director shall review the information submitted pursuant to subsection 1 and NAC 445A.910, and shall notify the holder of the permit in writing within 30 days after receipt of that information whether:
Added to NAC by Environmental Comm'n, eff. 7-22-87; A 10-21-87-Substituted in revision for NAC 445.427
NRS 445A.425, 445A.465