Nevada Administrative Code
Chapter 445A - Water Controls
MINING FACILITIES
Permits for Facilities
Section 445A.394 - Application for permit: Submission; contents
Current through September 16, 2024
1. To obtain a permit to construct, operate and close permanently a facility, the owner or operator of the proposed facility or the designated agent of the owner or operator must submit to the Department a written application signed by the owner or, if the owner does not operate the facility, the operator of the facility or his or her designated agent. The application must be accompanied by the appropriate fee established pursuant to NAC 445A.232.
2. An application for a permit must contain:
3. New applications or requests for major modifications to existing permits must be submitted to the Department at least 165 days before the date on which the applicant wishes to initiate construction.
Added to NAC by Environmental Comm'n, eff. 9-1-89-Substituted in revision for NAC 445.24288
NRS 445A.425, 445A.465