Section 445A.445 - Procedure upon unplanned temporary closure of process component
Current through September 16, 2024
1. In the event of an unplanned temporary closure of one or more process components, the holder of the permit shall:
2. The Department shall approve or disapprove the proposed procedures for permanent closure within 30 days after they are submitted to the Department.
3. Unless the Department has granted an extension pursuant to subparagraph (2) of paragraph (b) of subsection 1 , within 270 days after the Department has been notified of the unplanned temporary closure, the holder of the permit shall initiate the approved procedures for permanent closure.
4. If the holder of the permit fails to inform the Department of an unplanned temporary closure as required pursuant to subsection 1 and the Department otherwise becomes aware of such closure, the Department may:
Added to NAC by Environmental Comm'n, eff. 9-1-89-Substituted in revision for NAC 445.24384; A by R046-18A, eff. 8/21/2018; A by R046-18AP, eff. 8/30/2018
NRS 445A.425, 445A.465