Nevada Administrative Code
Chapter 445A - Water Controls
FINANCIAL ASSISTANCE FOR CONSTRUCTION OF WASTEWATER TREATMENT WORKS AND POLLUTION CONTROL PROJECTS
Requirements for Projects
Section 445A.799 - Oversight inspections; final construction inspection
Current through September 16, 2024
1. The Division may conduct oversight inspections during the construction of a project. The primary purpose of any such inspection must be to ascertain that the recipient is constructing the project according to applicable contract requirements. The first inspection must normally be conducted at the time the project is 10 percent complete. Subsequent inspections must be conducted only if they are deemed necessary by the Division.
2. The Division shall conduct a final construction inspection of each project. The primary purpose of this inspection must be to ascertain that the project has been constructed according to the approved plans and specifications and to ensure that required mitigation measures have been implemented. At the time of the inspection, the completion date for the project must be established for the purpose of beginning the 1-year period for certification of the performance of the project.
Added to NAC by Environmental Comm'n, eff. 9-19-90-Substituted in revision for NAC 445.42172
NRS 445A.135