Nevada Administrative Code
Chapter 445A - Water Controls
FINANCIAL ASSISTANCE FOR CONSTRUCTION OF WASTEWATER TREATMENT WORKS AND POLLUTION CONTROL PROJECTS
Requirements for Projects
Section 445A.797 - Notification of Division regarding steps in construction and beginning of operation of project

Universal Citation: NV Admin Code 445A.797

Current through September 16, 2024

A recipient of financial assistance shall notify the Division promptly in writing of:

1. The award of the prime construction contract for the project.

2. The beginning of construction of the project, stating the date on which he or she anticipates construction will be completed.

3. Any substantial change in the scope of the project. No such change may be undertaken until it has been approved in writing by the Division.

4. The cessation of all major construction work on the project, in any case where the cessation of work is expected to or does continue for 30 days or more.

5. Any circumstance or condition that is expected to or does delay the completion of construction for 90 days or more after the anticipated date of completion reported pursuant to subsection 2.

6. The completion of construction of the project.

7. The beginning of the operation of the project.

Added to NAC by Environmental Comm'n, eff. 9-19-90-Substituted in revision for NAC 445.4217

NRS 445A.135

Disclaimer: These regulations may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.