Section 445A.793 - Period for award of prime construction contract; extension of period
Current through September 16, 2024
1. Except as otherwise provided in subsection 2, a recipient of financial assistance shall award the prime construction contract within 90 days after the Division approves the award of the contract. If the contract is not awarded within that time, the agreement for financial assistance is null and void.
2. The Division may, upon the request of a recipient, grant an extension of the time provided by subsection 1 in any case where unusual or extenuating circumstances exist. Any request for an extension must be made in writing and must set forth facts justifying the extension.
Added to NAC by Environmental Comm'n, eff. 9-19-90; A by R115-10, 1-13-2011-Substituted in revision for NAC 445.42166