Nevada Administrative Code
Chapter 445A - Water Controls
FINANCIAL ASSISTANCE FOR CONSTRUCTION OF WASTEWATER TREATMENT WORKS AND POLLUTION CONTROL PROJECTS
Requirements for Projects
Section 445A.785 - Amount of infiltration and inflow into sewer system
Current through September 16, 2024
1. Except as otherwise provided in this subsection, an applicant shall demonstrate to the satisfaction of the Division that each sewer system discharging into the proposed treatment works project is not or will not be subject to excessive infiltration or inflow. Inflow into combined sewers shall not be considered excessive in any event.
2. If the rate of inflow results or will result in chronic operational problems, the applicant shall perform a study of the sewer system to determine the quantity of excessive inflow and propose a program to eliminate the problem.
3. If the applicant believes that any specific portion of the sewer system is subject to excessive infiltration, the applicant may confirm that belief through a cost-effect analysis and propose a program of rehabilitation to eliminate the problem.
4. If an existing sewer system is subject to excessive operation and maintenance costs, overflows or blockages because of deterioration or overloading of the system, the applicant may perform an analysis of the system and propose a program of sewer replacement to eliminate or substantially reduce the problem.
Added to NAC by Environmental Comm'n, eff. 9-19-90-Substituted in revision for NAC 445.42158
NRS 445A.135