Nevada Administrative Code
Chapter 445A - Water Controls
FINANCIAL ASSISTANCE FOR CONSTRUCTION OF WASTEWATER TREATMENT WORKS AND POLLUTION CONTROL PROJECTS
Requirements for Projects
Section 445A.782 - Use of value engineering
Current through September 16, 2024
1. The applicant shall conduct value engineering if the total estimated cost of building the treatment works is more than $10,000,000.
2. Any recommendations derived from the value engineering must be implemented to the extent feasible.
3. As used in this section, "value engineering" means a specialized technique for controlling costs which uses a systematic and creative approach to identify and to focus on any unnecessary cost to reduce the cost of a project without affecting the reliability or efficiency of the project.
Added to NAC by Environmental Comm'n, eff. 9-19-90-Substituted in revision for NAC 445.42155
NRS 445A.135