Nevada Administrative Code
Chapter 444 - Sanitation
SOLID WASTE DISPOSAL
Provisions Applicable to Solid Waste Management Systems
Section 444.6405 - Permit to operate disposal site: Requirement; exemptions; application

Universal Citation: NV Admin Code 444.6405

Current through September 16, 2024

1. Except as otherwise provided in subsection 2, the owner or operator of a disposal site must obtain a permit to operate the site from the appropriate solid waste management authority.

2. The following sites are exempt from the provisions of subsection 1:

(a) Composting bins which are operated at a personal residence for personal use; and

(b) Municipal composting operations for yard wastes.

3. The owner or operator of a proposed disposal site must obtain the permit before the construction or operation of that site. An application for the permit must be submitted at least 180 days before the anticipated start of construction, to allow sufficient time for the review and issuance of the permit.

Added to NAC by Environmental Comm'n, eff. 11-8-93; A 11-9-95; 10-3-96; R105-02, 10-18-2002

NRS 444.560

Disclaimer: These regulations may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.