1. The construction of a nitrogen removal wastewater treatment unit must be inspected and verified by an engineer. The inspections must be conducted when:
(a) The
absorption trenches have been excavated or, if an elevated mound system is to
be used, when the basal area of the mound has been scarified;
(b) The distribution piping has been placed
in the aggregate;
(c) The system
has been covered with soil; and
(d)
All the pumps, switches, alarms, aeration units and other components associated
with the individual sewage disposal system have been installed. The engineer or
homeowner, as appropriate, shall verify that the operational liquid levels are
set as specified by the design plans.
2. The engineer shall, within 30 days after the date on which the construction of the system is completed, submit a letter to the administrative authority stating that the system was constructed in accordance with the approved plans.
Added to NAC by Bd. of Health by R129-98, eff. 3-25-99; A by R100-07, 10-31-2007
NRS 439.200, 444.650
Disclaimer: These regulations may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.