Upon receipt of notice of the Board's resolution granting final approval for a proposed water project, the Director will, if not already accomplished:
1. Direct the applicant or obligor to submit a processing fee of not more than 1.75 percent of the principal amount of the total financing for the water project which must be remitted to the Director in the time designated by the Director. The processing fee will be deposited with the State Treasurer for credit to the Fund for Water Projects and will be used to defray the cost of a water project incurred by the Director related to the financing of the water project.
2. Except for a municipal obligor, send the applicant an inducement letter:
Added to NAC by Dep't of Commerce, eff. 4-22-88; A 11-13-90; 7-6-92