If after a public hearing the Board tentatively approves a proposed water project, the Board may, depending on the size and scope of the project:

1. Grant final approval of the application by adopting a resolution containing the findings set forth in NAC 349.350 or, if the application was filed by a municipal obligor, as set forth in NAC 349.425, and direct the Department to proceed with financing; or

2. If required, direct the applicant to proceed with the preparation of final plans, specifications and contract documents for submission to the Board for its subsequent review and final approval.

Added to NAC by Dep't of Commerce, eff. 4-22-88; A 11-13-90

NRS 349.946

Disclaimer: These regulations may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.