The Administrator shall review the preliminary plans of a project and the accompanying report submitted pursuant to NAC 341.351 and determine the high performance building design measures that must be incorporated into the design of the project to ensure that the project will achieve the efficiencies in the use of energy and water set forth in NAC 341.346. In reaching this determination, the Administrator shall consider, in addition to the information provided by the design consultant or project manager pursuant to NAC 341.351:

1. The initial cost of the high performance building design measures in relation to the budget for the project set forth in the State's capital improvement program.

2. The simple payback period of the high performance building design measures.

3. Any other information that the Administrator considers to be relevant to the determination.

Added to NAC by Pub. Works Bd. by R207-09, eff. 10-15-2010; A by R105-11 & R106-11, 5-30-2012; A by R072-24A, eff. 11/15/2024

NRS 341.091, 341.110

Disclaimer: These regulations may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.