Nevada Administrative Code
Chapter 338 - Public Works Projects
PROCEDURES FOR AWARDING CONTRACTS
Qualification of Bidders: Prime Contractors
Section 338.250 - Application for qualification; eligibility to bid on public work
Current through December 12, 2024
1. To qualify to bid on one or more contracts for public works, a prime contractor must:
2. The Division will specify:
3. If the application is for qualification for a 2-year period, the prime contractor must indicate on the application:
4. If the prime contractor is qualified to receive the preference set forth in NRS 338.13844, the prime contractor must indicate on the application his or her qualification for the preference.
5. An application must contain the signature of the prime contractor who is submitting the application.
6. The submission of a materially incomplete or falsified application or the failure of a prime contractor to disclose information in the application may be grounds for a delay in the qualification of the prime contractor or the denial or revocation of the qualification of a bidder.
Added to NAC by Pub. Works Bd. by R085-01, eff. 12-17-2001; A by R095-04, 12-15-2004; R189-07, 4-17-2008; R097-09 & R098-09, 10-15-2010; R100-11, 5-30-2012