Nevada Administrative Code
Chapter 338 - Public Works Projects
PROCEDURES FOR AWARDING CONTRACTS
General Provisions
Section 338.144 - "Substantial completion" defined
Universal Citation: NV Admin Code 338.144
Current through December 12, 2024
"Substantial completion" means that the construction of a public work is, in accordance with the contract documents, sufficiently complete that the owner can occupy and utilize the public work for its intended use.
Added to NAC by Pub. Works Bd. by R095-04, eff. 12-15-2004
NRS 338.1375, 338.1376
Disclaimer: These regulations may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.