Nevada Administrative Code
Chapter 338 - Public Works Projects
CONTRACTS INVOLVING CONSTRUCTION MANAGERS AT RISK
Contracts Between Construction Managers at Risk and Subcontractors to Provide Labor, Materials or Equipment on Projects
Section 338.630 - Proposals: Opening; qualifications
Universal Citation: NV Admin Code 338.630
Current through December 31, 2024
1. A construction manager at risk shall open proposals submitted by subcontractors who were qualified to submit proposals in accordance with the provisions of subsection 7 of NRS 338.16995.
2. Before the construction manager at risk opens a proposal submitted by a subcontractor, the construction manager at risk must confirm that the proposal was:
(a) Submitted by a subcontractor who was determined to be qualified to submit a proposal in the trade or for the scope of work for which the subcontractor has submitted a proposal;
(b) Submitted by a subcontractor who attended the preproposal meeting; and
(c) Timely received by the construction manager at risk.
3. If a proposal does not satisfy the requirements of subsection 2, the construction manager at risk must return the proposal unopened to the subcontractor who submitted the proposal.
Added to NAC by Pub. Works Bd. by R099-11, eff. 5-30-2012
NRS 338.16995, 341.070, 341.110
Disclaimer: These regulations may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.