Nevada Administrative Code
Chapter 338 - Public Works Projects
CONTRACTS INVOLVING CONSTRUCTION MANAGERS AT RISK
Contracts Between Construction Managers at Risk and Subcontractors to Provide Labor, Materials or Equipment on Projects
Section 338.570 - Applicability
Universal Citation: NV Admin Code 338.570
Current through December 31, 2024
The provisions of NRS 338.16991 and 338.16995 and NAC 338.550 to 338.640, inclusive, apply only to a subcontract for which the estimated value is at least 1 percent of the total estimated cost of the construction of the public work.
Added to NAC by Pub. Works Bd. by R099-11, eff. 5-30-2012
NRS 338.16991, 338.16995, 341.070, 341.110
Disclaimer: These regulations may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.