Nevada Administrative Code
Chapter 338 - Public Works Projects
CONTRACTS INVOLVING CONSTRUCTION MANAGERS AT RISK
Contracts Between Construction Managers at Risk and Subcontractors to Provide Labor, Materials or Equipment on Projects
- Section 338.550 - Definitions
- Section 338.555 - "Application for qualification" defined
- Section 338.560 - "Construction manager at risk" defined
- Section 338.565 - "Proposal" defined
- Section 338.570 - Applicability
- Section 338.580 - Submission of applications for qualification
- Section 338.590 - Procedure for determining qualification of applicants
- Section 338.600 - Appeal of determination that subcontractor not qualified to submit proposal; hearing
- Section 338.610 - Notice of request for proposals
- Section 338.620 - Proposals: When considered responsive; process if fewer than three received; envelopes must be time stamped
- Section 338.630 - Proposals: Opening; qualifications
- Section 338.640 - Procedure after opening proposals
Disclaimer: These regulations may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.