Nebraska Administrative Code
Topic - TRANSPORTATION, DEPARTMENT OF
Title 412 - NEBRASKA DEPARTMENT OF TRANSPORTATION - ROADWAY DESIGN DIVISION
Chapter 4 - When Use of Public Private Partnerships may be Appropriate
Section 412-4-004 - CRITERIA TO WEIGH IN ANALYZING WHEN USE OF P3 MAY BE APPROPRIATE FOR DELIVERY OF A DEPARTMENT TRANSPORTATION PROJECT
Current through September 17, 2024
004.01A The Director of Transportation ("The Director") or designee will make an initial determination whether any proposed project will be considered for use of an Alternative Project Delivery Method or whether the project should be developed under the traditional design-bid build method of Neb. Rev. Stat. § 39-1348 et seq. If a proposed project is selected by the Director as a candidate for an alternative project delivery method, then the following criteria shall be applied in determining whether to use P3. The Director reserves the right to reconsider the use of P3 or another alternative delivery method whenever such reconsideration is in the best interest of the Department.
004.01B Subject to the provisions of Section 01.05, the following are qualitative considerations that the Department may evaluate when determining whether it is appropriate to use a P3 delivery method:
004.01C Subject to the provisions of 01.05, the following are capital planning, budgetary, and other monetary considerations that the Department may take into account when determining whether it is appropriate to use a P3 delivery method: