013.01 A structural project shall be considered technically feasible when it can and will be designed, constructed, and operated to accomplish the purpose(s) for which it was planned utilizing accepted engineering and other technical principles and concepts. Technical data and information to be provided in the feasibility report should include, but is not limited to, the following:

013.01A A detailed discussion of the plan of development selected for the project;

013.01B A description of all field investigations made to substantiate the feasibility report;

013.01C Maps, drawings, charts, tables, etc., used as a basis for the feasibility report;

013.01D A description of the water and land rights associated with the project and pertinent water supply and water quality information, if appropriate;

013.01E A detailed discussion of each component of the final plan preparation including, when applicable:
013.01E1 Required geologic investigation;

013.01E2 Required hydrologic data;

013.01E3 Design criteria for final design including, but not limited to, soil mechanics, hydraulic, hydrologic, structural, embankments and foundation criteria.

013.02 A non-structural project shall be considered to be technically feasible when it can and will be designed and carried out to accomplish the purpose(s) for which it was planned. Data necessary to establish the technical feasibility should include, but is not limited to the following:

013.02A A detailed discussion of the plan of development designed for the project, including techniques to be utilized in all aspects of the project;

013.02B A description of field or research investigations utilized to substantiate the project conception;

013.02C A description of the water and/or land rights necessary for project continuation, if applicable;

013.02D A discussion of the anticipated effects, if any, of the proposed project upon the development and/or operation of existing or envisioned structural measures including a brief description of any such measure.

Disclaimer: These regulations may not be the most recent version. Nebraska may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.