Nebraska Administrative Code
Topic - NATURAL RESOURCE COMMISSION
Title 256 - RULES AND REGULATIONS GOVERNING THE ADMINISTRATION OF THE RESOURCES DEVELOPMENT FUND
Chapter 2 - APPLICATION PROCEDURES AND REQUIREMENTS
Section 256-2-008 - Public Hearing and Notification

Current through September 17, 2024

Except for projects requesting less than $ 100,000 from the Fund, the applicant shall conduct at least one public hearing on all aspects of the proposed project or program prior to submission of the formal application and feasibility report. Notice of the hearing shall be provided to the general public by the publication, at least ten days prior thereto, in a newspaper or newspapers of general circulation within the project or program area. A copy of such notice will be provided to the Director. Information gained from the hearing, including a summary of testimony presented, is to be forwarded with the application.

Disclaimer: These regulations may not be the most recent version. Nebraska may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.