Nebraska Administrative Code
Topic - LABOR, DEPARTMENT OF
Title 229 - DEPARTMENT OF LABOR
Chapter 20 - POWER BOILERS - NEW INSTALLATIONS
Section 229-20-011

Current through March 20, 2024

Power Boiler External Piping shall be designed, constructed, installed and inspected in accordance with the requirements of ASME B 31.1, Power Piping, and bears the ASME Certification Mark with the appropriate Designator.

A. Each steam outlet from a boiler, except safety valve and water-column connections, shall be fitted with a stop valve located as close as practicable to the boiler. When a stop valve is so located that water can accumulate, ample drains shall be provided. The drainage shall be piped to a safe location and shall not be discharged on the top of the boiler or its setting.

B. When boilers provided with manholes are connected to a common steam main, the steam connection from each boiler shall be fitted with two (2) stop valves having an ample free-blowing drain between them. The discharge of the drain shall be piped clear of the boiler setting. The stop valve arrangement shall consist of one automatic non-return valve next to the boiler and second valve of the outside screw and yoke type.

C. All other Boiler Proper piping and/or External Piping, valves, gauges, and devices shall comply with the rules as stated in ASME B 31.1 and ASME Section I.

Disclaimer: These regulations may not be the most recent version. Nebraska may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.