An applicant for a specific license must:
(A) Be qualified by reason of training and experience to use the material in question for the purpose requested according to Title 180 in such a manner as to minimize danger to public health and safety or property;
(B) Have proposed equipment, facilities, and procedures are adequate to minimize danger to the public health and safety or property;
(C) Demonstrate that the issuance of the license will not be inimical to the health and safety of the public; and
(D) Satisfy any applicable special requirements in 180 NAC 3-013, 180 NAC 3-014, or 180 NAC 3-015, 180 NAC 5, 180 NAC 7, 180 NAC 12, 180 NAC 14 or 180 NAC 19.
011.01 ENVIRONMENTAL REPORT, COMMENCEMENT OF CONSTRUCTION. In the case of an application for a license to receive and possess radioactive material for commercial waste management, source material milling, or for the conduct of any other activity which the Department determines will significantly affect the quality of the environment, the Department, before commencement of construction of the plant or facility in which the activity will be conducted, has concluded, after weighing the environmental, economic, technical and other benefits against environmental costs and considering available alternatives, that the action called for is the issuance of the proposed license, with any appropriate conditions to protect environmental values. Commencement of construction prior to such conclusion is grounds for denial of a license to receive and possess radioactive material in such plant or facility. As used in this paragraph the term "commencement of construction" means any clearing of land, excavation or other substantial action that would adversely affect the environment of a site. The term does not mean site exploration, necessary roads for site exploration, borings to determine foundation conditions, or other preconstruction monitoring or testing to establish background information related to the suitability of the site or the protection of the environmental values.
011.02 FINANCIAL SURETY ARRANGEMENTS FOR SITE RECLAMATION. The following applies to financial surety arrangements for site reclamation.