Section 180-19-005 - START OF CONSTRUCTION

Current through March 20, 2024

The applicant may not begin construction of a new irradiator before the submission of both a license application for the irradiator and the fee required by 180 NAC 18-005 to the Department. Any activities undertaken before the issuance of a license are entirely at the risk of the applicant and have no bearing on the issuance of license with respect to any statutory requirements or rules, regulations, and orders issued under the Nebraska Radiation Control Act, as amended.

Disclaimer: These regulations may not be the most recent version. Nebraska may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.