Nebraska Administrative Code
Topic - HEALTH AND HUMAN SERVICES SYSTEM
Title 179 - PUBLIC WATER SYSTEMS
Chapter 7 - SITING, DESIGN AND CONSTRUCTION OF PUBLIC WATER SYSTEMS
Section 179-7-003 - SUBMISSION OF PLANS AND SPECIFICATIONS
Current through September 17, 2024
Plans and specifications for all major construction, extension or alteration to public water systems must be prepared by an engineer and must be submitted to the Director for review and written approval prior to the beginning of construction, except as provided in 179 NAC 7-004. Upon approval of the plans and specifications the Director will issue a construction permit. A construction permit is valid for a period of two years from the date of issuance. If construction is not started within two years from the issuance of the permit, the owner and/or the engineer must request a time extension in writing prior to the expiration of the construction permit and the Director must approve it with an expiration date in order for it to continue to be valid.
003.01 The plans and specifications:
003.02 Record drawings must be submitted to the Department within one year of the project placement into service date.
003.03 Review of Plans and Specifications
When review of the plans and specifications does not indicate substantial conformance to Neb. Rev. Stat. §§ 71-5301 to 71-5313 or regulations in Title 179 NAC 7, or if inadequate information is provided for a complete review, a comment letter will be issued by the Department to the engineer. The issues identified in the Department's comment letter must be addressed within 60 calendar days from the date of issuance of the comment letter unless the owner and/or the engineer request in writing and the Department approves an extension of time. If the engineer does not respond in writing to the Department's comment letter within 60 calendar days from the issuance of the comment letter, the Department will deny the construction permit for the project. When a project is denied for construction, new sets of plans and specifications, along with a review fee per Title 179 NAC 7-005, must be submitted for review and written approval prior to starting construction.
003.04 The Department may deny approval of plans and specifications for failure to comply with any of the provisions of Neb. Rev. Stat. §§ 71-5301 to 71-5313 or 179 NAC 7. The Department will inform the engineer and the public water system owner, in writing, of the factual basis for the denial and the statutory or regulatory provisions supporting the decision. The denial will become final 30 days after the mailing of the notice, unless the public water system owner, within the 30-day period, requests a hearing in writing. The hearing shall be conducted in accordance with the Nebraska Administrative Procedure Act and 184 NAC 1, the Department's Rules of Practice and Procedure for Administrative hearings.