003.01 General Planning requirements. Loan applicants will prepare an engineering report which defines the project, its purpose, and its scope.
003.02 Recipients will satisfy the Cost and Effectiveness Analysis requirements in accordance with Chapter 3. 002.02C.
003.03 Loan applicants will have plans and specifications prepared by professional engineers registered in the state of Nebraska and submitted to the Department for review and approval.
003.04 Effect of Approval or Certification of Documents. Review or approval of engineering reports, design drawings and specifications, or other documents by the Department does not relieve the loan recipient of its responsibility to properly plan, design, build, and effectively operate and maintain the Non point Source Control Systems and land acquisition and source water protection projects described in the loan in accordance with the CWSRF Act or DWSRF Act, regulations, permits, and good management practices.
003.05 Access to ground water monitoring wells is to be provided at all reasonable times for such purposes as inspection, monitoring, building, operation, rehabilitation, and replacement.
003.06 Use Ordinances or User Charge Systems: The loan recipient is to include ordinance provisions required by the Department for any use ordinance or user charge system enacted in relation to the nonpoint source control system or the land acquisition and source water protection project.