Nebraska Administrative Code
Topic - ENVIRONMENT AND ENERGY
Title 131 - RULES AND REGULATIONS FOR THE WASTEWATER TREATMENT FACILITIES AND DRINKING WATER CONSTRUCTION ASSISTANCE PROGRAM
Chapter 3 - GENERAL REQUIREMENTS FOR CWSRF and DWSRF PROJECTS
Section 131-3-001 - Wastewater Treatment Works, Nonpoint Source Control System, and Public Water System Land Acquisition and Source Water Protection Projects will satisfy the following
Universal Citation: 131 NE Admin Rules and Regs ch 3 ยง 001
Current through September 17, 2024
001.01 Procurement Standards for Engineering Services and Construction Contracts. Loan applicants will use their own procurement procedures which reflect applicable federal, state, and local laws and regulations.
001.01A For engineering services to be
eligible, the loan applicant will submit to the Department the appropriate
professional services agreement for planning, design, and/or construction
administration services. The Department will review the agreement(s) for
eligibility.
001.01B The Department
will review costs and will provide assistance for engineering costs which are
considered reasonable and acceptable. Costs that appear excessive or
unjustified may be limited for loan participation. The Department may provide
an allowance for planning and/or design costs. The Department may use 40 CFR
Part 35 Appendix B dated February 17, 1984 as a tool to determine the allowance
for engineering services.
001.01C
For construction contracts the loan recipient will follow the procedures under
Chapter 3, 002.03A.
001.02 Public Participation. Loan applicants will conduct a minimum of the following:
001.02A. A public meeting when facility
planning alternatives have been developed, but before an alternative has been
selected, to discuss all alternatives under consideration and the reasons for
rejection of others. Public notice must occur not less than 30 days prior to
the public meeting.
001.02B.
public hearing prior to formal adoption of a facility plan to discuss the
proposed facility plan, financial aspects of the project, proposed annual
residential and industrial user charges, and any needed mitigation measures.
Public notice must occur at least 45 days prior to the date of the
hearing.
001.03 Environmental Review. Loan applicants will conduct environmental review of projects using the following procedures.
001.03A. 40 CFR Part 6 - Procedures for
Implementing the National Environmental Policy Act and Assessing the
Environmental Effects Abroad of EPA Actions, as amended, is hereby adopted and
incorporated herein.
001.04 Construction Contracts. Construction contracts are to include:
001.04A
Requirements for the contractor of the construction project to post separate
performance and payment bonds or other security approved by the Department in
the amount of the bid:
001.04B A
complete statement of work to be performed, including design drawings,
specifications, and the required performance schedule:
001.04C The terms and conditions of the
subagreement to be awarded:
001.04D
A clear explanation of the loan recipient's method of bidding and evaluating
bid prices, and its method for awarding the subagreement:
001.04E Any applicable wage determination
requirements:
001.04F The deadline
and place to submit bids:
001.04G
Requirement for bid bond for 5% of the contractor's bid.
001.05 Contract Award and Construction Activities.
001.05A Construction Contract
Procurement and Bid Document Review and Approval. Loan recipients will use
their own procurement procedures which reflect applicable federal, state, and
local laws and regulations.
001.05A1 The
Department will review the bidding documents and authorize award of the
construction contract.
001.05A2 In
case of a single bid, the loan recipient may return the bid to the bidder
unopened, promptly notify the Department, and re-advertise the
project.
001.05B
Monitoring Construction. The loan recipient is to provide and maintain
competent and adequate engineering supervision and resident inspection during
construction.
001.05B1 Department
Inspections. Department officials will monitor and inspect project
construction. Department officials may also attend construction progress
meetings. The purpose of these inspections will be to ensure that construction
is progressing on schedule in accordance with approved plans/specifications and
to determine compliance with terms of the loan. The loan recipient is required
to correct all the deficiencies which are brought to their attention as a
result of Department inspection. When the project is considered substantially
complete and is operating as intended, the Department will perform a final
inspection.
001.05B2 Initiation of
operation. The loan recipient is to notify the Department in writing of the
date of initiation of operation.
001.05C Change Orders. Change orders are to
be in the form of a written document, issued by the loan recipient to a
contractor, which alters the price, time of completion, or any other
requirement(s') of the original contract documents.
001.05C1 The loan recipient is responsible
for the adequate and prompt management of change orders.
001.05C2 Change orders will be submitted to
the Department with documentation to support the cost and scope of work defined
in the change order for review and approval by the Department.
001.05C3 The loan recipient may request
additional funds for approved change orders if the additional work results in
costs which will exceed the funds allocated to the project under the original
contract.
001.05C4 Additional funds
may be made available to the loan recipient if the change order costs are
considered eligible and allowable subject to availability of funds.
001.05D Operation and Maintenance
Manual. The operation and maintenance manual provides the information and
guidance for the day-to-day effective and efficient operation and maintenance
of the project. The loan recipient is to submit a draft of the manual as well
as a final operation and maintenance manual to the Department.
001.05E Force Account. Project work which
will be performed by the employees of the loan recipient may be categorized as
force account. All significant elements of work are to be performed through the
competitive bidding process.
001.05E1 The loan
recipient may elect to complete certain project work by force account. In order
to undertake this responsibility, the loan recipient will:
001.05E1.a Seek prior approval from the
Department:
001.05E1.b Document
that this work will be performed in an efficient and cost-effective manner:
and
001.05E1.c Ensure that specific
details of the force account effort are included in the loan as part of the
project scope.
001.05E2
The loan recipient will receive loan disbursements for force account work upon
receipt of documentation which verifies the costs incurred. Only direct labor
and material cost is eligible for loan participation under this
provision.
001.05FSmall
Purchases. The loan recipient may use small purchase provisions in accordance
with applicable federal, state, and local laws and regulations, with prior
approval of the Department. Payment for this work will require the submittal of
documentation such as invoices and receipts.
Disclaimer: These regulations may not be the most recent version. Nebraska may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.