Nebraska Administrative Code
Topic - ENVIRONMENT AND ENERGY
Title 129 - AIR QUALITY REGULATIONS
Chapter 3 - CONSTRUCTION PERMITS
Section 129-3-003 - Permit Action

Current through March 20, 2024

The Director will publish notice of intent to approve or disapprove the application in accordance with the procedures of Chapter 10.

003.01 A construction permit issued for any construction, reconstruction, or modification, does not relieve the owner or operator from the responsibility to comply with the applicable portions of the State Implementation Plan (SIP) control strategy. The source is to comply with all conditions of the construction permit. Any permit noncompliance will constitute a violation of the State Act and the Act, and is grounds for enforcement action or permit revocation.

003.02 Approval to construct will become invalid if construction is not commenced within 18 months after approval of the construction permit, if construction is discontinued for a period of 18 months or more, or if construction is not completed within a reasonable time. The Director may extend the 18-month period upon a satisfactory showing by the permittee, made at least 30 days before the approval to construct becomes invalid, that the complexity of the construction, reconstruction, or modification requires additional time.

Disclaimer: These regulations may not be the most recent version. Nebraska may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.