Section 126-1-006 - Commence New Source Construction

Current through March 20, 2024

"Commence New Source Construction" means the owner or operator has:

006.01 Begun, or caused to begin as part of a continuous onsite construction program:

006.01A Any placement, assembly, or installation of facilities or equipment;

006.01B Significant site preparation work including clearing, excavation, or removal of existing buildings, structures, or facilities which is necessary for the placement, assembly, or installation of new source facilities or equipment; or

006.02 Entered into a binding contractual obligation for the purchase of facilities or equipment which is intended to be used in its operation within a reasonable time and which cannot be terminated or modified without substantial loss.

Disclaimer: These regulations may not be the most recent version. Nebraska may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.