005.01 The owner of a dwelling or non-dwelling facility or the owner's designee, proposing to construct, reconstruct, alter, modify, or make a repair not exempted in Chapter 2 to an onsite wastewater treatment system not covered by a general permit will apply for and obtain a construction permit from the Department prior to construction of the system.
005.02 The design of all onsite wastewater treatment systems not covered by a general permit will be approved by the Department prior to issuance of a construction permit.
005.03 Onsite wastewater treatment systems will be designed in a manner and using engineering standards, as determined by the Department, necessary to protect public health, the environment, surface water, and groundwater.
005.04 A construction permit will be issued in the name of the facility owner for the legal location of the facility.
005.05 A construction permit is valid for two years from date of issuance. Prior to expiration, the owner may submit a written request for reauthorization or extension from the Department. If approved, the reauthorization or extension will be subject to requirements of regulations in effect at the time the reauthorization or extension is issued, and such reauthorization or extension will be valid for no more than one year from date of reissuance. Additional reauthorization or extension may be requested in writing prior to expiration.
005.06 The onsite wastewater treatment system will be constructed, reconstructed, altered, or modified according to the Department approved design and standards contained in the construction permit.
005.07 The owner is to notify the Department of any changes to the approved design or changes in wastewater characteristics (quality or quantity) and obtain Department approval prior to changes being made in the system. If the Department determines that any such changes are significant modifications to the previously approved design, the Department may require submittal of a new application and application fee. If a new construction permit is issued, the previous construction permit will become null and void.
005.08 The Department may require, as a construction permit condition, submittal of an operation and maintenance manual or plan to provide for the proper operation of the onsite wastewater treatment system.
005.09 The Department may require, as a construction permit condition, submittal of a groundwater monitoring plan for an onsite wastewater treatment system if there is a potential for groundwater pollution.