Nebraska Administrative Code
Topic - ENVIRONMENT AND ENERGY
Title 124 - ONSITE WASTEWATER TREATMENT SYSTEMS
Chapter 3 - PERMITS
Section 124-3-004 - Construction and Operating Permit Application

Current through September 17, 2024

004.01 The construction permit and the operating permit for a single system are covered by one application.

004.02 The owner of a dwelling or non-dwelling facility will submit a complete permit application on a form provided by the Department and include any supporting documents or reports requested.

004.03 The plans, specifications, reports, and other technical documents submitted as part of the application will be prepared and properly stamped and signed by a Professional Engineer.

004.04 The Department may require additional information to ensure proper engineering design and operation.

004.05 The permit application fee (see Appendix A) is to be submitted to the Department with the application. For subdivisions, a fee will be due for each lot subject to approval.

Disclaimer: These regulations may not be the most recent version. Nebraska may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.