Notice of Intent to Operate Prior to operation of a Class I or III injection well(s) and/or mineral production well(s), the permittee must submit a notice of completion construction to the Director and provide the following information as required by the permit to obtain approval to operate:

004.01 All available logging and testing program data on the well(s);

004.02 A demonstration of mechanical integrity pursuant to Chapter 18 of this Title;

004.03 The results of the formation testing program;

004.04 The compatibility of injected materials with fluids in the injection zone and minerals in both the injection zone and the confining zone; and

004.05 The status of corrective action on defective wells in the area of review.

Disclaimer: These regulations may not be the most recent version. Nebraska may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.