Nebraska Administrative Code
Topic - ENVIRONMENT AND ENERGY
Title 122 - NEBRASKA DEPARTMENT OF ENVIRONMENTAL QUALITY
Chapter 17 - CONSTRUCTION AND SITING REQUIREMENTS; CLASS I, III, and V INJECTION WELLS AND MINERAL PRODUCTION WELLS
Section 122-17-003 - Specific Requirements for Class III Injection Wells

Current through March 20, 2024

003.01 All Class III well designs shall be submitted by a professional engineer.

003.02 All new Class III wells shall be cased and cemented to prevent the migration of fluids into or between underground sources of drinking water. The casing and cement used in construction of each newly drilled well shall be designed for the life expectancy of the well. In determining and specifying casing and cementing requirements, the following factors shall be considered:

003.02A. Depth to the injection zone;

003.02B. Injection pressure, external pressure, internal pressure, axial loading, etc.;

003.02C. Hole size;

003.02D. Size and grade of all casing strings (wall thickness, diameter, nominal weight, length, joint specification, and construction material);

003.02E. Corrosiveness of injected fluids and formation fluids;

003.02F. Lithology of injection and confining zones; and

003.02G. Type and grade of cement.

003.03 Each Class III well or group of wells utilizing a positive displacement pump shall be equipped with both high and low pressure safety switches which will shut down the pump in case of pressure increase over the authorized pressure or sudden pressure loss.

003.04 Appropriate logs and other tests shall be conducted during the drilling and construction of new Class III wells. A descriptive report interpreting the results of such logs and tests shall be prepared by a qualified log analyst and submitted to the Director. The logs and tests appropriate to each type of Class III well shall be determined based on the intended function, depth, construction and other characteristics of the well, availability of similar data in the area of the drilling site and the need for additional information that may arise from time to time as the construction of the well progresses. At a minimum, such logs and tests shall include deviation checks conducted on all holes where pilot holes and reaming are used, at sufficiently frequent intervals to assure that vertical avenues for fluid migration in the form of diverging holes are not created during drilling.

003.05 Where the injection zone is a water bearing formation, the following information concerning the injection zone shall be determined or calculated for new Class III wells:

003.05A. Fluid pressure;

003.05B. Temperature;

003.05C. Fracture pressure;

003.05D. Other physical and chemical characteristics of the injection zone;

003.05E. Physical and chemical characteristics of the formation fluids; and

003.05F. Compatibility of injected fluids with formation fluids.

003.06 Where the injection formation is not a water bearing formation, the information in Section 002.02D3 of this Chapter must be submitted.

003.07 Where injection is into a formation which contains water with less than 10,000 mg/l TDS, monitoring wells shall be completed into the injection zone and into any underground sources of drinking water above the injection zone which could be affected by the mining operation. These wells shall be located in such a fashion as to detect any migration of injection fluids, process by-products, or formation fluids outside the mining area or zone. If the operation may be affected by subsidence or catastrophic collapse, the monitoring wells shall be located so that they will not be physically affected.

003.08 Where injection is into a formation which does not contain water with less than 10,000 mg/l TDS, no monitoring wells are necessary in the injection stratum.

003.09 Where the injection wells penetrate an USDW in an area subject to subsidence or catastrophic collapse an adequate number of monitoring wells shall be completed into the USDW to detect any movement of injected fluids, process by-products or formation fluids into the USDW. The monitoring wells shall be located outside the physical influence of the subsidence or catastrophic collapse.

003.10 In determining the number, location, construction and frequency of monitoring of the monitoring wells the following criteria shall be considered:

003.10A. The population relying on the USDW affected or potentially affected by the injection operation;

003.10B. The proximity of the injection operation to points of withdrawal of drinking water;

003.10C. The local geology and hydrology;

003.10D. The operating pressures and whether a negative pressure gradient is being maintained;

003.10E. The toxicity and volume of the injected fluid, the formation water, and the process by-products; and

003.10F. The injection well density.

Disclaimer: These regulations may not be the most recent version. Nebraska may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.