Nebraska Administrative Code
Topic - ENVIRONMENT AND ENERGY
Title 122 - NEBRASKA DEPARTMENT OF ENVIRONMENTAL QUALITY
Chapter 10 - CLASS V INJECTION WELL AUTHORIZATION APPLICATION; INFORMATION REQUIREMENTS
Section 122-10-001

Current through March 20, 2024

Any person who proposes or operates a Class V underground injection well, which meets the requirements in Chapter 6 of this Title, shall submit an application to the Director. For new injection wells, the application shall be filed at least 180 days before the construction is planned to begin, including plans for testing, drilling and construction.

Disclaimer: These regulations may not be the most recent version. Nebraska may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.