A new source or new discharger wishing requesting to discharge pollutants into waters of the state will file an NPDES application at the same time as application is made to the Department for a construction permit under NDEE Title 123 for a new source, not less than 180 days prior to commencement of discharge.

Disclaimer: These regulations may not be the most recent version. Nebraska may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.