Rule 38.5.8607 - ENERGY UTILITY PLANNED OUTAGES

Universal Citation: MT Admin Rules 38.5.8607

Current through Register Vol. 18, September 20, 2024

(1) In the event that service must be interrupted for more than two hours for planned work on utility facilities or equipment, the work shall be done at a time which will cause minimal inconvenience to customers, including consideration of weather conditions. The utility shall attempt to notify each affected customer at least 24 hours in advance of the interruption, either personally or, when personal notification would be impractical, by advance notice in local media outlets.

69-3-103, MCA; IMP, 69-3-201, MCA;

Disclaimer: These regulations may not be the most recent version. Montana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.