Administrative Rules of Montana
Department 38 - PUBLIC SERVICE REGULATION
Chapter 38.5 - UTILITY DIVISION
Subchapter 38.5.84 - Small Generator Interconnection
Rule 38.5.8403 - INTERCONNECTION REQUESTS
Universal Citation: MT Admin Rules 38.5.8403
Current through Register Vol. 6, March 22, 2024
(1) Applicants seeking to interconnect a small generator facility shall submit an interconnection request using a standard form filed with the commission by the EDC that owns the electric distribution system to which interconnection is sought. All fees for processing interconnection requests must be paid prior to acceptance of the interconnection request by the utility.
69-3-103, MCA; IMP, 69-3-102, MCA;
Disclaimer: These regulations may not be the most recent version. Montana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.